Stoke College

Low-Impact Groundworks for Educational Facilities

Project
Overview

Get In Touch
Get In Touch

Quick Facts

  • Location: Stoke College, Stoke-on-Trent

  • Project Type: New college hub construction

  • Sector: Educational

  • Status: Active construction

  • Key Challenge: Working 6 metres from occupied student building

Sustainability
Approach

New College Hub Taking Shape in Stoke

Work is underway on a new college hub in Stoke located just 6 metres from an active student building.

To minimise our impact on this sensitive location, we're using HVO biofuel in our heavy machinery (cutting emissions by 90%) and electric tools to reduce both fumes and noise levels.
 

This project demonstrates our commitment to sustainable construction that respects the communities we work in.

Gradient Purple Blue

February 2025

Foundations Begin

Foundations begin, including stitch drilling of a retaining wall toe to enable a new corner pad.

0b0c2f53-421a-408e-8238-a5e7f0308624.jpeg

June 2025

Foul & Surface

All foul and surface drains to the hub are complete.

277540b5-95de-44e1-8115-bb7e68a72e83.jpeg

August 2025

LV Trench and Cable Pull Complete

The cobra was successfully pulled through the car park's existing duct, and a new rope has been secured at both ends. The low-voltage (LV) trench to the substation has been completed.

a5438ba8-d92a-4a6f-93d3-fc50ed216f74.jpeg

6th September 2025

Concrete Beam & Jablite Installation

U-bars have been cast into the concrete beams. We will drill and resin the dowel bars through the U-bars and tie the 393 mesh to them. 75mm jablite has been placed over all services and drains.

4th September 2025

Structural Slab Pour Preparation

We have arranged a volumetric truck to pour the structural slab. Dowels will be fixed to both building footings/slabs with U-bars set in to tie the mesh and upstand bars on Sunday.

63b73f62-c155-4513-9622-16a4785ba7f2.jpeg

7th September

Main Slab Poured

We have poured a 300mm thick slab with 393 top and bottom mesh suspended on three mass-fill strip footings.

8aba1229-c683-4802-b3b8-0d65493ff432.jpeg
5c97eda7-dd76-4f66-b133-29c24a5df3c2.jpeg

14th September 2025

Concrete Trimming & Rebar Order

The team will be on-site this Tuesday to trim the concrete back to the hub upstand and expose the steel for the link upstand tie-in.

Eurotool Groundworks

Build in Progress

diagram of school by bbc

Featured with BBC 

diagram of school by bbc